Surface Preparation
Remove all loose material including dust, oil and grease. Minimum application depth should be 20mm. Repair edges should be cut to depth to avoid feather-edging. Dampen bare concrete with clean, cold water. Remove any standing water. Briefly warm the area using a blowlamp or gas torch. This helps to accelerate curing.
Warning Do not mix the product for more than 4 minutes. Use immediately. Watco Freezer Patch cures very quickly and the mixed product must be applied and finished within 10 minutes.
Mixing
Mixing must be carried out in an ambient temperature above 5ºC. If mixing at temperatures below 5ºC, pre-warm the mixing vessel with warm (approximately 25- 30ºC) water. Remove the bag of powder and pour 2 litres of clean, cold water into the plastic container. Gradually add all the powder, mixing thoroughly. Continue mixing to produce a smooth workable mortar.
Application
Trowel Watco Freezer Patch firmly into place using a steel trowel or float (available from Watco). The trowel can be wiped with clean, cold water to make finishing easier. Apply the product at a minimum 20mm thickness, if using at a temperature range of -20ºC to 5ºC.